Policy Formulation 2018 to 2024
2016
- West Oxfordshire District Council (WODC) submit expression of interest to Garden Villages, Towns and Cities programme
2017
- WODC selected as 1 of 14 sponsored Garden Villages, Towns and Cities
2018
- Area Action Plan Issues Paper published for consultations
- West Oxfordshire Local Plan to 2031 adopted
- Specialist evidence commissioned
- Community Forum established. 1st meeting developing aspirations for the OCGV
- 2nd community forum: to develop perceptions of need for various groups of people
- Eynsham Parish Council submit Neighbourhood Plan for pre-examination consultation
2019
- 3rd Community forum visits to other Garden Villages / towns to consider "the good, the bad and the ugly" & gather inspiration.
- Launch of thegardenvillage.org website.
- 4th community forum - exploring emerging opportunities and constraints
- 4 day community design charrette over 100 attendees. Outcomes, 3 preferred options
- Exhibition of design charrette outcomes in WODC offices
- Exhibition of design charrette outcomes in Eynsham library
- Oxford Brookes yr 2 urban design students study Salt Cross and present their masterplan proposals to the community
- OCGV AAP Preferred Options consultation
- Pre submission draft of AAP published. Public consultation on draft AAP
2020
- WODC submitted the draft AAP to planning inspectorate for examination
- Grosvenor Developments Ltd submitted an outline planning application to WODC
2022
- Planning Inspectorate hearings of the Salt Cross examination
2023
- Planning Inspectorate found Salt Cross Area Action Plan to be legally sound subject to main modifications. Including a modification to policy 2 Net Zero
- Community legal case against the Planning Inspectorate. 2 day hearings at the High Court
2024
- High Court Judgement finds in favour of the Community in relation to policy 2 Net Zero
- WODC to modify policy 2 Net Zero in accordance with central government December 2023 Ministerial Statement whilst remaining ambitious regarding Net Zero outcomes
- Decision making: 2025 to 2026
2025
- Salt Cross Area Action Plan policy 2 Net Zero hearing
- Approval of Salt Cross Area Action Plan by Planning Inspector subject to Main Modifications
- Consultation on Policy 2 Main Modifications
2026
- Inspector’s final report published
- Adoption of Salt Cross Area Action Plan
- Grosvenor Developments Ltd outline planning application to be updated in line with the adopted Salt Cross Area Action Plan.
- WODC resolution to grant planning permission.
2027
- Complete Section106 agreement
- Grant of Outline Planning Permission
- Discharge of pre-commencement decisions
Implementation: Anticipated 2028 to 2043
2028
- Phase 1a pre-application design and consultation work
- Submission of 1st phase reserved matters application (RMA)
- Determination of the 1st phase RMA
- Discharge of pre-commencement conditions
2029
- Mobilisation
- Commencement on site
- 1st completions
2029 to 2043
- Onsite delivery – phasing to be agreed
NB. The overall timeline may need to be extended to allow more time for design work on and subsequent approval of enabling infrastructure RMAs eg the first sections of the Spine Road.